BOW WHARF – SUGGESTED REASONS FOR REFUSAL

Extract from officers report for the Bow Wharf Development committee meeting on 17th Jule 2013. http://modgov.towerhamlets.gov.uk/mgAi.aspx?ID=44289#mgDocuments

Extract from officers report for the Bow Wharf Developement committee meeting on 17th Jule 2013 (see all documents here)

Applications will go back to the Committee on 17th July at 5.30  (see here)

See full document here
Suggested Reasons for Refusal –
Full Panning Permission
5.3The following reason relates to Member’s concern regarding the impacts on the heritage aspects of the site, with emphasis on the height of the proposal:
5.4The proposal would represent an unacceptable form of development with regard to design, appearance, height, bulk, scale and massing which would fail to preserve or enhance the open character and appearance of this part of the Regents Canal Conservation Area.  As such, the proposal would be contrary to strategic policy SP10 of the adopted Core Strategy (2010), policies DM25 and DM27 of the adopted Managing Development Document (2013), the National Planning Policy Framework and the guidance contained within the Regents Canal Conservation Area Appraisal. These policies seek to ensure development preserves or enhance the character and appearance of the Regents Canal Conservation Area and that development takes account of local context.
5.5Officer Comment: The issue of design is a planning issue, and accordingly it is considered by officers that such a reason for refusal is based on planning merits, and could be reasonably defended at appeal by officers.

Reason for Refusal No. 2
5.6Officers have grouped the two concerns raised by members regarding the overdevelopment of the site due to density, and lack of s106 contribution into one reason.
5.7The proposal would fail to accord with table 3.2 of policy 3.4 of the London Plan (2011), and would therefore result in the overdevelopment of the subject site, without securing appropriate levels of financial contributions, including health contributions, to mitigate against the impacts of such density. The proposal is therefore contrary to the adopted Planning Obligations SPD (2012), policy SP13 of the Core Strategy (2010) and the National Planning Policy Framework, which seek to ensure that the impacts of development are mitigated through planning obligations.
5.8Officer Comment: It is the view of officers that a reason for refusal regarding density and lack of s106 contribution is weak in planning terms.
5.9The proposal exceeds the density matrix within the London Plan marginally, by 6 habitable rooms per hectare (density range of 200 – 450 habitable rooms per hectare; proposal seeks 456 habitable rooms per hectare). Whilst in the simplest of numerical terms the density exceeds the matrix, the intent of the London Plan is to maximise the highest possible intensity of use compatible with the local context. The proposal itself is not considered to demonstrate any symptoms of overdevelopment, and no particular concerns with relation to the impacts of the additional 6 habitable rooms per hectare have been raised.
5.10Paragraph 173 of the National Planning Policy Framework (2012) set out that:
“Pursuing sustainable development requires careful attention to viability and costs in plan-making and decision-making. Plans should be deliverable. Therefore, the sites and the scale of development identified in the plan should not be subject to such a scale of obligations and policy burdens that their ability to be developed viably is threatened. To ensure viability, the costs of any requirements likely to be applied to development, such as requirements for affordable housing, standards, infrastructure contributions or other requirements should, when taking into account the normal cost of development and mitigation, provide competitive returns to a willing land owner and willing developer to enable the development to be deliverable”
5.11Additionally, the Council’s Planning Obligations SPD acknowledges that in certain circumstances the viability of a scheme is jeopardised due to site constraints or other factors and that in these circumstances viability appraisals are required for officers to assess.
5.12The s106 contributions secured have been subject to a viability assessment, which has been independently assessed by consultants on behalf of the Council, and found that the financial contributions secured represent the maximum amount which the scheme can reasonably afford.
5.13Accordingly, it is the view of officers that reason for refusal number 2 carries limited weightin planning terms, given that the proposal does not exhibit the typical symptoms of over-development, and proposes a financial obligations package which is reasonable when considered in the context of the scheme viability.

Reason for Refusal No. 3
5.14Officers have drafted the following reason, with regard to the failure to secure min 35% affordable housing:
5.15The proposal fails to secure a minimum of 35% affordable housing, and is therefore contrary to policies SP02(3a) of the Core Strategy 2010 and DM3 of the Managing Development Document (2013), which seek the delivery of 35% – 50% affordable housing in major developments.
5.16Officer Comment: It is the view of officers that a reason for refusal regarding the amount of affordable housing is not appropriate in this instance.
5.17Policy 3.12 of the London Plan (2011) – ‘Negotiating affordable housing on individual private residential and mixed-use schemes’ notes:
‘A) The maximum reasonable amount of affordable housing should be sought when negotiating on individual private residential and mixed use schemes, having regard to…
B) Negotiations on sites should take account of their individual circumstances including development viability, the availability of public subsidy, the implications of phased development including provisions for reappraising the viability of schemes prior to implementation and other scheme requirements’
5.18Policy SP02(3a) of the Core Strategy (2010) notes:
 “Set an overall strategic target for affordable homes of 50% until 2025. This will be achieved by:
a) Requiring 35% – 50% affordable homes on sites providing 10 new residential units or more (subject to viability)”
5.19Accordingly, together with the NPPF position as outlined in paragraph 5.10 of this report, it is enshrined in policy that financial viability is a material consideration in the delivery of affordable housing.
5.20The application being considered has been subject to detailed financial viability review, officers have taken the view on advice ofa financial viability consultant appointed by the Council, that the proposed level of affordable housing is the maximum reasonable amount of affordable housing that the scheme can deliver.
5.21In the event that planning permission is refused, it is important to add a reason for refusal setting out that no legal agreement securing financial contributions has been entered into.
Additional Reason for Refusal (No. 4).
5.22In the event that planning permission is refused, it is important to add a reason for refusal setting out that no legal agreement securing financial contributions has been entered into.
5.23No planning obligations in the form of financial contributions have been secured to mitigate the impacts of the development. As a result, the proposal fails to meet the requirements of policy SP13 of the adopted Core Strategy (2010) and the Planning Obligations Supplementary Planning Document (2012), which seek to agree planning obligations between the Local Planning Authority and developers to mitigate, compensate and prescribe matters relating to the development.
5.24Officer Comment: Officers suggest that if members are minded to refuse planning permission, they also include this as a reason for refusal. This would ensure that if the applicant appeals and were not to enter into a legal agreement that the Inspector would also consider the implications of the lack of any financial contributions or affordable housing being provided, allowing for the negotiation and provision of appropriate financial mitigation.
Conservation Area Consent– reason for refusal
5.25In the absence of an approved planning permission for the re-development of the site, the demolition of the existing buildings would leave an undeveloped site which would represent a blight on the character and appearance of the Regents Canal Conservation Area, contrary to strategic policy SP10 of the adopted Core Strategy (2012), policy DM27 of the adopted Managing Development Document (2013), the National Planning Policy Framework and the guidance within the Regents Canal Conservation Area Appraisal. These policies seek to ensure development preserves or enhances the character and appearance of the Regents Canal Conservation Area.
6.0IMPLICATIONS OF THE DECISION
6.1Following the refusal of the application the following options are open to the Applicant. These would include (though not be limited to):
1) The applicant could appeal the decisions and apply for an award of costs against the Council. Planning Inspectorate guidance on appeals sets out in paragraph B20 that:
“Planning authorities are not bound to accept the recommendations of their officers. However, if officers’ professional or technical advice is not followed, authorities will need to show reasonable planning grounds for taking a contrary decision and produce relevant evidence on appeal to support the decision in all respects. If they fail to do so, costs may be awarded against the Council’’.
2) There are two financial implications arising from appeals against the Council’s decisions. Firstly, whilst parties to a planning appeal are normally expected to bear their own costs, the Planning Inspectorate may award costs against either party on grounds of “unreasonable behaviour”. Secondly, the Inspector will be entitled to consider whether proposed planning obligations meet the tests of CIL Regulations 2010 (Regulation 122).
3) The Inspector will be entitled to consider the type and amount of affordable housing. This could result in the developers being able to provide affordable rented housing at up to 80% of market rents across this site, as opposed to the current proposed offer which secures the affordable rent at POD levels (especially in view of the Planning Inspector’s Report which dealt with the Examination In Public into the Managing Development Document). Similarly, the developer may elect to either renegotiate planning obligations previously agreed or prepare a unilateral undertaking for a subsequent appeal which might well result in a lesser S.106 planning obligations package (both in terms of financial and non-financial obligations negotiated by your officers).
6.2Should Members resolve to refuse planning permission, officers would seek to defend any appeal made by the applicant.
7.0CONCLUSION
7.1All relevant policies and considerations have been taken into account. Whilst officers’ remain satisfied that planning permission and conservation area consent for this proposed development should be GRANTED, subject to suitable conditions and the signing ofa S.106 Agreement, Members are directed to the draft reasons for refusal and officers comments, viewed alongside the previous reports and update reports presented to the Development Committee and determine the planning application as appropriate.
7.2If Members are minded to refuse planning permission, officers recommend that this be on the basis of drafted reasons for refusal No.s 1 and 4.

All documents here can be seen – follow the links

Site At Bow Wharf Adjoining Regents Canal And Old Ford Road, Old Ford Road, London (PA/11/03371 – 3372)

Supporting documents:

Leave a Reply

Your email address will not be published. Required fields are marked *